    Amt to be paid on the date of this agreement.           20%
   Amt to be paid on Completion of footings.                   10%
    Amt to be paid on Completion of Stilt Floor Slab  .          10%
    Amt to be paid on Completion of Ground Floor Slab.          10%
    Amt to be paid on Completion of First Floor Slab .           10%
    Amt to be paid on Completion of Second Floor Slab .         10%
    Amt to be paid on Completion of Third Floor Slab .          10%
    Amt  to be paid on completion of Fourth Floor slab .            5%
    Amt to be paid on Completion of walls  .                    5%
    Amt to be paid on Completion of flooring .                   5%
    Final Payments to be paid at the time of handing

      over the vacant possession of the Schedule C flat .   

       

 5%